T-0001

Johnson Ferry Road from the Chattahoochee River to Abernathy Road and Abernathy Road from Johnson Ferry to Roswell Road


View T-0001 Abernathy Road/Johnson Ferry Road Widening in a larger map

Project Description

Johnson Ferry Road from the Chattahoochee River to Abernathy Road

Johnson Ferry will be widened from Columns Drive in Cobb County to Riverside Drive in Fulton County, including the bridge over the Chattahoochee, to accommodate six 12’ travel lanes, a 16’ raised median, 4’ bike lanes, 2’ grass strip and 10’ sidewalks.

Johnson Ferry Road will then drop down to four 11’ travel lanes from Riverside Drive to Abernathy Road, with a 16’ raised grassed center median, 4’ bike lanes, 2’ grass strip and 8’ sidewalks.

Abernathy from Johnson Ferry Road to Roswell Road

Abernathy Road will be widened to four 11’ travel lanes, two in each direction, with a variable 16’ to 32’ raised median and with 4’ bike lanes, 2’ grass strip and 8’ sidewalks.

The intersection at Abernathy and Roswell will be improved by adding dual left turn lanes and a median at the intersection for all approaches.

Project Status

A Public Information Meeting for this road widening project was held in October 2011. You can download responses to the questions posed by members of the public at this meeting.

1/19/2012

  • Project is currently 62 % complete.
  • Clearing and mass grading is 98% complete.
  • Culvert construction is complete on Abernathy Road.
  • Construction of the new Bridge # 1 over the Chattahoochee River is complete.
  • Demo and reconstruction of the existing bridge # 2 is underway and is scheduled for completion by December 2012.
  • Stage two construction is 90% complete.

12/1/2011 - Construction is underway. Georgia DOT contractor CW Matthews will be paving new road alignments during the daytime and nighttime hours. Listed below are the traffic shifts that will be in place. Project is approximately 65% complete. Stage two construction began October 2011 that will include widening portions of Johnson Ferry Road from Columns Drive up station to River Valley Road. Traffic was shifted to the new bridge late October 2011. Work has begun on the rehabilitation of the existing bridge with a projected completion of November 2012.

Project Schedule

  • Project is currently 2% ahead of schedule to meet a December 31, 2012 completion.

First Quarter of 2012 Schedule

  • Stage two construction will be completed by the end of the 1st QTR.
  • Drainage structures will be completed on Abernathy from Brandon Mill Road to State Route 9 (Roswell Road).
  • The final stage three construction will begin in early February.
  • Bridge # 2 (existing bridge) demo will continue with the removal of the decking and the elevation change of the beams to match the newly built bridge # 1.
  • The stone work will begin on the Breakwater walls and is scheduled for completion in 1st qtr of 2012.
  • Construction is underway on the Woodcliff Brick wall # 4 next to Redding Drive and is scheduled for completion by the end of the 2nd QTR of 2012.
  • Curbing, sidewalk, and driveways will be completed on Abernathy from Brandon Mill to State Route 9.
  • Signals for the Brandon Mill Road and Wright Road intersections will be positioned in their permanent locations.
  • Utility relocation will continue on Abernathy from Wright Road to Cherry Tree Lane including major relocations in the Abernathy / State Route 9 intersection.

Additional Links

Notes

  • CW Matthews is the prime contractor

  • Barry Murray is the GDOT project manager

  • GDOT District Contact:

    • Bryant Poole
      District 7, Metro Atlanta
      770-986-1011